Case Study
Mentor Graphics: Data Centre BMS Upgrade
Sirus completed the upgrade of a BMS in an international data centre for Mentor Graphics in Shannon in 2018.
The Solution
The existing Allerton controllers were upgraded to PXC100-ED Siemens Controllers with a Desigo CC frontend. The system controls HVAC with high-temperature tolerances.
This project was conducted in a live environment and was carried out in a tight timeframe – all live work was completed successfully in the space of 10 working days.
The Result
The Mentor Graphics data centre upgrade project was conducted in a live environment with no interruptions to the running plant.
This project was successfully completed in a client defined timeframe in compliance with ISO 9001 Quality Management standards.
This job involved complete replacements of live MCC boards and also a retrofit of an existing board.
Sirus’ experience in data centre environments demonstrates our ability to seamlessly work with clients in live facilities ensuring there is no downtime throughout the project.
“The BAS execution overall was a big success! Thanks to all the Bristol-Myers Squibb, Jacobs and Sirus folks that were part of the BAS team for making that happen.”
David Wilson
Director Project Management Engineering
Bristol-Myers Squibb