by Sirus Engineering | Jun 8, 2021
The Sirus relationship with the site dates back to 2008 and the RC project. Subsequent projects since then have combined to make substantial state-of-the-art Qualified and Non-Qualified Building Management Systems (QBMS and nQBMS).
by Sirus Engineering | Apr 14, 2021
Sirus installed 2 no. 750 kW Air-cooled QUANTUM Turbocor Chillers to replace the two chillers which had been serving the hospital for the last 15+ years.
by Sirus Engineering | Jan 12, 2021
This turnkey project required the replacement of the existing RC Chiller with a 600kW Engie Quantum Chiller as well as installation of new pipework, valves, pumps and a plate heat exchanger.
by Sirus Engineering | Nov 6, 2020
Case Study RWE Npower: Power Plant BMS Supply, Install & Commission In 2010, RWE NPower constructed a new 2,200 MW Combined Cycle Gas Turbine (CCGT) Power Plant in Pembrokeshire Wales. The main contractor on this project was Alstom Power Ltd. & Alstom...
by Sirus Engineering | Jul 7, 2020
Sirus was engaged to provide a reliable laboratory controls solution for their R&D Laboratory to be integrated within the building automation and control system.